Question: 1 / 410

Which of the following is a characteristic of a technical performance measure (TPM)?

Only used in final evaluations

Measures cost efficiency

Tool for project control

A technical performance measure (TPM) is a key aspect of systems engineering that focuses on monitoring and evaluating the technical performance of a system throughout its lifecycle. The correct choice reflects that TPMs serve as tools for project control by providing measurable parameters that can indicate whether a project is on target to meet its performance goals.

TPMs help project managers and engineers assess how well the project is progressing against its technical objectives. By tracking these measures, stakeholders can make informed decisions about resource allocation, adjustments to project plans, and any necessary corrective actions if performance is not aligning with expectations. This monitoring is a continuous process, allowing for real-time feedback and adjustments rather than being limited to only the final evaluations or assessments.

In contrast, the other options do not align with the primary role of TPMs. While cost efficiency can be an important element of project success, it is not the specific focus of TPMs, which are more concerned with technical capabilities. Establishing project timelines pertains more to schedule management rather than technical performance, and final evaluations occur too late in the process to implement timely controls based on technical measures. Hence, the choice that describes TPMs as a tool for project control accurately captures their function in ensuring that the technical aspects of a project are maintained effectively throughout

Get further explanation with Examzify DeepDiveBeta

Establishes project timelines